PROCESS AREA - STRUCTURE SE1

The SE1 structure, made by steel, consist of three main independent structures and described as follow:
  • 1st Body - pipe rack: The maximum height is about 9,2m and the plan dimensions are about 10,0mx19,5m. The gravity loads, due to 3 piping levels, have been supported by 3 transversal frames, which have also the task to guarantee the transversal stability against wind and seismic loads. In longitudinal direction the horizontal stability is guarantee by vertical bracings.
  • 2nd Body - pipe rack: The maximum height is about 9,2m and the plan dimensions are about 12,0mx20,5m. The gravity loads, due to 3 piping levels, have been supported by 3 transversal frames, which have also the task to guarantee the transversal stability against wind and seismic loads. In longitudinal direction the horizontal stability is guarantee by vertical bracings.
  • 3rd Body - Shelter: The maximum height is about 23,0m and the plan dimensions are about 36,0mx18,0m. The gravity loads, due to the crane and one service platform, have been supported by 7 main transversal frames, which have also the task to guarantee the transversal stability against wind and seismic loads. In longitudinal direction the horizontal stability is guarantee by vertical bracings.
Process Area - SE1